Multiple sets of drilling rig mud tank systems have completed installation and commissioning work

Multiple sets of drilling rig mud tank systems have completed installation and commissioning work. The drilling rig mud tank system including shale shaker, desander, desilter/ mud cleaner, vacuum degasser, decanter centrifuge, trailer mounted mud tanks with tank accessories and roof cover, centrifugal pump, mud agitator, mud gun, etc.

As per client’s request, GN engineer will fly to client’s rig site to complete the installation and commissioning work. The installation and commissioning work including:
1. Functionality Check: Ensure that all components of the mud tank systems are functioning correctly. This includes mixing equipment, pumps, shakers, and other related machinery.
2. Safety measures: Verify that all safety measures are in place and that the systems comply with relevant safety standards and regulations.


3. Operational Training: Make sure that the crew is adequately trained to operate the new systems. This includes understanding the controls, troubleshooting common issues, and emergency procedures.
4. Environmental Compliance: Ensure that the mud tank systems are equipped to handle waste management and comply with environmental regulations to prevent any spillage or contamination.
5. Documentation: Complete all necessary documentation, including installation reports, commissioning certificates, and operational manuals. This documentation is crucial for future reference and compliance audits.
6. Maintenance: Establish a regular maintenance schedule to keep the mud tank systems in optimal condition. This will help in preventing unexpected downtime and prolonging the lifespan of the equipment.
7. Performance Monitoring: Implement a system for continuous monitoring of the mud tank systems’ performance. This will help in identifying any inefficiencies or issues early on and allow for timely corrective actions.


As one of the solids control system and drilling waste management system manufacturer in China, GN Solids Control can design and produce customized drilling rig mud tank systems according to client’s requirement. For more information, pls contact with GN solids engineer.

Deep-well drilling rig Mud tank system for Coalfield Geology

Recently one set of deep well drilling rig mud tank system for coalfield geology are ready for delivery for China drilling company. The mud tank system consists of 4 sets of mud tanks, 1 set of shale shaker, 1 set of mud cleaner, 1 set of middle speed decanter centrifuge and pumps, mud agitators, mixing hopper, etc.


The shale shaker model is GNZS594, which is a 4 panel linear motion shale shaker as primary separation of the solids control system, installed 4ea of composite material frame shaker screens on the shaker, the vibration strength is adjustable and up to 7.5G, the deck angle can be adjustable synchronously from both sides during working manually. The total screen area is 2.73m2.


The mud cleaner GNZS594J-2S12N is a combination of desander cone, desilter cone and 4 panel bottom shale shaker, with the same dimension shaker screen with shale shaker.The desander cone and desilter cone acts as the second phase separation and the third phase separation of the solids control system. Two units of centrifugal pump are as feeding pump of the desander cone and desilter cone.
The 4 sets of customized designed mud tanks installed with proper quantities of mud agitator, mud gun, mixing hopper and mud tank accessories, electrical control system.


The middle speed decanter centrifuge GNLW452 acts as the fourth phase separation equipment of the solids control system, the separation cut point is 5~7 microns.
As one of the solids control system manufacturer for drilling rigs in China, GN solids control can design and produce complete mud tank system with all the solids control equipments, if you need a mud tank system for oil and gas drilling, geothermal drilling, core bed methane drilling, water well drilling, horizontal directional drilling, coalfield geology and other types drilling, pls contact with GN Solids control.

 

1500HP Drilling Rig Solids Control System for Africa Project

Recently one package of 1500HP drilling rig solids control system are ready for delivery to Africa project. The technical configuration is as below:


1. Solids control shale shaker GNZS594J-SHBJ, 3 units, each unit with 4 panel shaker screen which is with composite material frame and stainless steel wire mesh 2 or 3 layers by 4 sides pretension.
2. Centrifugal degasser GNZCQ-1200, 1 unit
3. Desander unit GNZJ591J-M2SF, 1 unit , with 2 ea of 10 inch desander cone, the general treating capacity is up to 1000gpm of drilling fluids.
4. Desilter unit GNZJ591J-M16NF, 1 unit, with 16 ea of 4 inch desilter cone, the total treating capacity is up to 1500gpm of drilling mud.


5. Centrifugal pump in different size for different applications, including 5 units of GNSB8x6-14J (75KW) centrifugal pump, 3 units of GNSB8x6-13J (55KW) centrifugal pump, 5 units of GNSB4x3-12J (15KW) centrifugal pump and shear pump GNJBQ6*5-750 (75KW), 3 units of mixing hopper (H)JM-200, these centrifugal pump can be used as transfer pump, trip pump, mixing pump, charging pump, feeding pump.


6. High speed decanter centrifuge GNLW363D-GP, 1 unit, to separate the fine solids from drilling fluids and keep it balancing. The centrifuge is 14 inch bowl diameter with 50 inch bowl length, the max speed is up to 3600rpm and the max G force is 3063G, the separation cut point is 2~ 5microns, if need to separate more fine solids, chemical dosing unit can be used together with the centrifuge by adding chemicals in the inlet tube.
7. Mud agitators installed on the mud tank for drilling mud agitating and mixing, including 7 units of 20HP mud agitator, 2 units of 15HP mud agitator, 1 unit of 7.5HP mud agitator.
8, Customized mud tank system, including active tank, intermediate tank, suction tank, mixing tank,, reserve tank, trip tank,etc.